Port Connectivity Road Project

In Progress
Start Date:
15 June 2022
Completion Date:
31 December 2025
Budget:
₹12,450 Crores
Multiple Port Locations across India

Construction of a 6-lane elevated corridor connecting the port to national highways to improve logistics efficiency.

Project Overview

A Deep Water Port (or deep-sea / deep-water seaport) is a port that has sufficiently deep draft (i.e. depth of water) to allow very large vessels with high deadweight tonnage (DWT) to dock safely without needing to lighten their load. These ports often require deep navigation channels, large turning basins, strong breakwaters, and substantial infrastructure for loading/unloading, storage, multimodal connectivity (roads, rails), etc.

Project Objectives

  • Increase the combined cargo handling capacity by 425 MTPA across participating ports
  • Reduce average vessel turnaround time by 40%
  • Implement digital port management systems at all major ports
  • Develop dedicated freight corridors connecting ports to industrial clusters
  • Enhance port connectivity through road, rail, and inland waterway improvements

Project Documents

Project Overview Presentation

Download

Environmental Impact Assessment

Download

Quarterly Progress Report Q3 2023

Download

Key Components

Infrastructure Development

Construction of new berths, deepening of channels and basins, and modernization of cargo handling equipment

Infrastructure Development

Construction of new berths, deepening of channels and basins, and modernization of cargo handling equipment

Infrastructure Development

Construction of new berths, deepening of channels and basins, and modernization of cargo handling equipment